Which below-the-hook standard applies to your lift

Two questions decide it and neither is about the beam. A decision tree, what each region's documents actually cover, and the same spreader beam run through three routes: 55.7 percent, 59.6 percent and 31.0 percent on identical steel.

Updated 23 August 2026 · Companion tool: Spreader Beam Design Calculator

01

The question is not which standard is best

It is what the device is and where the lift happens. Both answers are usually already fixed before anyone opens a standard, which is why arguing about the standard first wastes the argument.

Engineers reach for this question in the wrong order surprisingly often. The order that works is:

What is the thing? A device that hangs below the hook and is not part of the load is a lifting device, and the lifting device standards apply to it. A padeye welded to a vessel is part of the vessel: the code that governs the vessel governs its attachment, and a lifting device standard has nothing to say about it. A sling, a shackle or a hook is an accessory, rated by its own standard, and neither of the other two families applies.

Where is the lift? Design standards are national or regional. A device designed in one jurisdiction for use in another is designed to the standard of the place it will be used, and that is a contractual question as much as a technical one.

Who is imposing something on top? A marine warranty surveyor, a client specification, or a corporate standard can impose factors above whatever the design route asks for. Those are additional, not alternative.

Get those three answers and the standard is decided. Get them in the wrong order and you end up defending a choice made for the wrong reason.

02

The decision, as a tree

Work down it. Most lifts are resolved by the second question, and the ones that are not are the ones worth thinking hard about.

  1. 01Is the device below the hook, part of the load, or an accessory?

    Below the hook
    A lifting device standard governs the design. Spreader beams, lifting beams, C-hooks, coil grabs, vacuum lifters, magnet frames. Continue to the next question.
    Welded to or part of the load
    The code that governs the load governs the attachment. A padeye on a pressure vessel is a pressure-equipment attachment first, and its local shell stresses are a pressure-equipment problem. A padeye on a building steel member is checked to the steel code.
    An accessory between the two
    It is rated, not designed, by its own product standard. Slings, shackles, hooks, eyebolts, links. Your job is to work out the force and compare it with the rating.
  2. 02Where is the lift taking place?

    United States
    ASME BTH-1 for design, ASME B30.20 for use. They are used together and neither is complete alone. BTH-1 derives its allowables through a design factor tied to a design category and a service class tied to expected cycles.
    European Economic Area
    EN 13155 for the load basis and proof, EN 1993 for the steel. EN 13155 deliberately does not carry member resistances, so a European route is always two documents.
    Canada
    There is no Canadian below-the-hook device standard. CSA S16 gives steel resistances but no lifting load factor, so the demand-side factor is a declared project value that somebody has to own.
    Australia
    AS 4991 for lifting devices, with AS 4100 for the steel. The same two-document structure as Europe, with a different pair of documents.
  3. 03Is anything imposing factors on top?

    A marine warranty scope
    A marine operations standard sets the demand, on top of whichever resistance code you use. Dynamic amplification, skew load and consequence factors. These are additional to the design route, not an alternative to it.
    A client or corporate specification
    Read it before starting, not at the review. Client specifications commonly impose a minimum design category, a minimum design factor, or a proof-test regime, and they are the cheapest thing on this list to discover late.
    Nothing
    The design route's own factors are the whole demand side. Record that it is nothing, explicitly. An absence somebody confirmed is different from an absence nobody looked for.

03

The United States: a pair, not a standard

Design criteria in one document and safety requirements in another, used together. Citing one alone is the commonest error on a US job.

Two consequences worth carrying:

The design category is a decision about knowledge, not about importance. The higher category exists for devices whose loads are less well defined or whose environment is less controlled. Choosing it because a lift feels important, rather than because the load is uncertain, produces a heavier device without addressing anything.

The service class is a decision about cycles. A one-off lift and a device that runs a hundred times a shift are different problems, and this is where that difference enters the calculation.

04

Europe: two documents, deliberately

The harmonised standard carries the load basis and the proof conditions. The steel code carries the resistances. Neither works alone and neither pretends to.

The European route therefore produces two families of check on one device: conditions under multiples of the rated load, from the harmonised standard, and member resistances, from the structural code. In the worked example below both appear, and it is the harmonised standard's conditions that come closest to governing.

05

Canada, and what an honest gap looks like

There is no Canadian below-the-hook device standard. That is not a problem with anybody's calculator; it is a fact about the standards landscape, and the only wrong response is to hide it.

There are three responses to that, and only one of them is defensible.

Borrow a factor from another country's device standard. Tempting, quick, and wrong, because a factor extracted from one document's scheme does not carry that scheme's other provisions with it. A design factor tied to a design category means something inside the standard that defines both.

Design to another country's standard outright. Perfectly reasonable, if the project agrees to it and it is stated. This is a contractual decision, not a technical dodge.

Declare the load factor as a project value. Somebody with authority states the factor, records why, and owns it. It is then visible on every result, and a reviewer can argue with it.

The third is what Xarpis does, and the behaviour is worth showing rather than describing.

Spreader Beam Design Calculator · computed at page render

The Canadian route with nothing declared

The same 10 t, 6 m spreader beam, on the Canadian route, with the project load factor left at zero.

Checks that computedthe arrangement solve and the sling angle limit2
Member resistance checks that computedthe route has no load factor to apply0
Equilibrium tilt angle0.0%
Sling angle within declared limits75.9%

The rigging still solves, because geometry does not need a standard. The steel checks refuse to produce a number, and they say why. That refusal is the feature: an engine that filled the gap silently would be inventing the most consequential input in the calculation.

Open this example in the calculator

Australia has a device standard, and which pair you need is decided before any of the engineering starts.

06

The same beam, three routes

Identical steel, identical geometry, identical lift. The three routes disagree by nearly two to one on the padeye weld, and every one of those answers is correct within its own scheme.

The device is the calculator's default arrangement: 10 t on a 6 m circular hollow section spreader, slings at 60 degrees from horizontal, with a 25 mm padeye at each end.

Spreader Beam Design Calculator · computed at page render

The ASME route, Design Category B, Service Class 0

Allowables derived through the design factor tied to the category, with the service class governing the fatigue side.

Axial compression3.7%
Major-axis bending including LTB10.4%
Combined axial and bending14.1%
Padeye pin bearing50.8%
Padeye attachment weld55.7%
Checks that computed12
Governing check: Sling angle within declared limits75.9% utilisationPass

Note what governs: not the steel, but the sling angle limit. On a well-proportioned spreader the geometry is usually the binding constraint long before the section is.

Open this example in the calculator

Spreader Beam Design Calculator · computed at page render

The European route, 16 000 declared cycles

Two families of check on one device: the harmonised standard's conditions under multiples of the rated load, and the structural code's member resistances.

Elastic condition at 2 x rated loadfrom the harmonised standard55.9%
Yielded condition at 3 x rated loadfrom the harmonised standard62.4%
Flexural bucklingfrom the structural code4.1%
Bending and lateral-torsional buckling8.2%
Padeye pin connection62.4%
Padeye attachment weldagainst 55.7% on the ASME route59.6%
Checks that computed11
Governing check: Sling angle within declared limits75.9% utilisationPass

The harmonised standard's proof conditions land close to the structural checks rather than beside them, which is the point of having both. A device that satisfies the member resistances and fails the elastic condition at twice its rated load is not a compliant device.

Open this example in the calculator

Spreader Beam Design Calculator · computed at page render

The Canadian route, project load factor 1.50 declared

The same steel resistances, with a demand-side factor that somebody on the project has stated and owns.

Declared project load factornot from a Canadian device standard, because there is not one1.50
Axial compression2.1%
Bending4.5%
Padeye pin connection29.5%
Padeye attachment weldagainst 55.7% and 59.6%31.0%
Checks that computed8
Governing check: Sling angle within declared limits75.9% utilisationPass

Lower than the other two, and that is exactly why the factor has to be declared and visible. The number is a consequence of the factor somebody chose, and a reviewer who cannot see the factor cannot review the result.

Open this example in the calculator
Same steel, same lift, three schemes. None of these numbers is more correct than the others; each is correct inside the document it came from, which is why the route has to be stated on the drawing.

The route is part of the answer. A utilisation without the route named beside it is not a result, because the same steel produces three of them.

07

Offshore, and the factors that arrive on top

A marine warranty scope does not replace a design route. It raises the demand the route is applied to, and it is not optional.

The relationship is a stack, not a choice:

  1. The design route decides how a resistance is computed and what a check has to satisfy.
  2. The marine warranty scope decides what demand goes into it, through factors on the load.
  3. The client specification may raise either.

That is why an offshore lift point is heavier than an identical onshore one. Nothing about the steel or the code changed; the demand entering the same check went up.

08

Six ways the standard question goes wrong

Five of them are scope errors. The sixth is the expensive one, and it is a silence.

1. The design standard cited alone. The US design criteria without the safety volume beside them. The device is calculated and its use is unaddressed.

2. The harmonised standard treated as a complete design code. It carries a load basis and proof conditions, not member resistances. A calculation citing it alone has not checked the beam against anything.

3. A lifting device standard applied to a padeye on a vessel. The attachment is part of the pressure equipment. Its local shell stresses are a pressure-equipment problem with its own accepted methods.

4. A factor lifted out of one scheme into another. A design factor tied to a design category is meaningless outside the standard that defines both.

5. The edition unstated. The European standard is now an amended 2020 edition; the US design standard is on 2023. A result that does not say which edition it was computed against cannot be re-checked.

6. A gap filled silently. The one that costs most. Where a jurisdiction has no device standard, the load factor is a decision. A calculation that supplies one without saying so has hidden the single most consequential input, and the reviewer has no way to know.

Common questions

Which standard applies to a spreader beam?
The one for the region the lift happens in, and it is usually a pair rather than a single document. In the United States a below-the-hook device is designed to ASME BTH-1 and used under ASME B30.20. In the European Economic Area it is EN 13155 for the load basis and proof conditions with EN 1993 for the member resistances. In Australia it is AS 4991 with AS 4100. Canada has no below-the-hook device standard at all, so a Canadian route needs a declared project load factor.
Is ASME BTH-1 enough on its own?
No. BTH-1 carries design criteria and ASME B30.20 carries the marking, construction, installation, inspection, testing, maintenance and operation requirements, and the two are used together. A device that satisfies the design criteria and is used outside the safety volume is a well-calculated device rather than a compliant one, and a specification citing only one of the pair has left half the obligation unstated.
Does EN 13155 tell me how to check the beam?
No, and it does not try to. EN 13155 carries the load basis and the proof conditions - what the device must satisfy under multiples of its rated load - and deliberately leaves member resistances to the structural code. A European route is therefore always two documents, EN 13155 alongside EN 1993, with the partial factors settled by the national annex where the lift happens.
What standard do I use for a lifting beam in Canada?
There is no Canadian below-the-hook lifting device standard. CSA S16 gives steel resistances but no lifting load factor to put against them, so the demand-side factor has to be a project decision that somebody states and owns. The alternatives are to design to another country's standard by agreement, or to declare the factor explicitly on the calculation. What is not defensible is borrowing a factor out of another standard's scheme, because a design factor tied to a design category means nothing outside the document that defines both.
Does the design route change the answer?
Yes, and by more than most people expect. The same 10 t spreader beam in this article's worked example gives a padeye attachment weld utilisation of 55.7 percent on the ASME route, 59.6 percent on the European route and 31.0 percent on the Canadian route with a 1.5 project load factor declared. None is more correct than the others; each is correct inside its own scheme, which is why the route belongs on the drawing beside the number.

Sources

Every document below is linked at its publisher or regulator. Xarpis reproduces no standard text; where a clause is named, the identifier is given so you can find it in your own copy.

  • ASME BTH-1Design of Below-the-Hook Lifting Devices

    ASME · paid document

    Structural, mechanical and electrical design criteria for below-the-hook lifting devices, used alongside ASME B30.20 which carries the safety requirements. The current edition is BTH-1-2023; Xarpis implements the 2020 edition and says so on every result.

  • ASME B30.20Below-the-Hook Lifting Devices

    ASME · paid document

    The safety half of the US below-the-hook pair: marking, construction, installation, inspection, testing, maintenance and operation. It requires the device to have been designed to BTH-1 and then governs everything that happens afterwards, which is why citing BTH-1 alone leaves half the obligation unstated.

  • EN 13155Cranes. Safety. Non-fixed load lifting attachments

    BSI (national adoption of the CEN standard) · paid document

    The harmonised European standard for non-fixed load lifting attachments - the family a spreader beam or lifting beam belongs to. It carries the load basis and the proof requirements, not member resistances, which is why an EN route needs EN 1993 alongside it. Now published as EN 13155:2020+A1:2025.

  • EN EurocodesEurocodes: Building the future

    European Commission, Joint Research Centre · free portal

    The Commission's own Eurocodes portal: the structure of EN 1990 to EN 1999, the database of Nationally Determined Parameters, and the second-generation timetable. The standards themselves are sold by the national bodies, but the NDP database is free and is what decides which partial factors apply in your country.

  • CSA standardsCSA Group store

    CSA Group · paid document

    The publisher of CSA S16 (design of steel structures) and CSA Z150 (mobile cranes). Worth knowing what is not here: there is no Canadian below-the-hook lifting device standard, which is why a Canadian design route has to take its load factor as a declared project value.

  • AS standardsStandards Australia store

    Standards Australia · paid document

    The publisher of AS 4991 (lifting devices), AS 4100 (steel structures) and AS 1418 (cranes, hoists and winches). Australian lifting practice sits on all three together, and none of them is free.

  • DNV-ST-N001Marine operations and marine warranty

    DNV · paid document

    The marine warranty standard behind most offshore lift factor sets: dynamic amplification, skew load and consequence factors, and the load cases a marine operation is planned against. Widely applied onshore by contract even though its scope is marine.

Run the check properly

Reading about a calculation is not the same as being able to hand one over. These tools produce the traceable record.

Something here wrong, or thinner than it should be? Tell us which paragraph and it gets rewritten. Articles carry the date they were last revised for exactly this reason.

Below-the-hook lifting device standard by region · Xarpis